Contract
Type:
Turbine overhauling, module upgrade (in EMC Badr
Workshop) and replacement, in addition to Minor and
Major gas (Centrifugal and reciprocating) Compressor
overhauling.
Location:
ELNG, SEGAS and Petrobel (Abu
Redais, Abu Mady and Portfoad Sites).
Start Date: October, 2006
Duration:
3 years and the contract was
renewed for two years ending October 2011.
Contract Description: High customer satisfaction and safe performance of the project with significance and appreciation by the client (NP). Our records constitutes over Hauling for Gas Turbine (Frame 5, Frame 7 & PGT102), combustion inspection, hot gas inspection, minor & major inspection, rotor Replacement, eddy currents and boroscope inspection, dry gas seal replacement, commissioning & alignment of pumps.
|
|