| Project: |
Installation of New BOG Feed 3" Pipe to 16 MD01 |
|
| Client: |
Spanish Egyptian Gas Company "SEGAS" |
| Location: |
Damietta, Egypt |
| Start Date: |
7th of June, 2009 |
| Duration: |
2 Months |
Brief: |
Fabricate new BOG line connecting 3" line to the existing St. line with hot tie in performing the non-destructive test (NDT), hydrostatic test and painting according to SEGAS Specs. |
| |
|
|
| Project: |
Installation of Internal Trays for vessels, columns & Towers, and Pre-commissioning for Rotating Equipment |
|
| |
| Client: |
Petrojet/E-Methanex |
| Location: |
Damietta-PortSaied, Egypt |
| Start Date: |
February 2009 to September 2009 |
| Duration: |
8 Months |
Brief: |
EMC Scope of work is mainly:
- Pre-commissioning for all types of rotating equipments (Pumps, Compressors, Air Fan Coolers, Blowers ... Etc.)
- Internals installation for Static Equipments (towers, vessels and reactors).
|
| |
|
|
| Project: |
Maintenance & Repair Of "HVAC" A/C Systems |
|
| Client: |
Egyptian Operating Company for Natural Gas
Liquefaction "ELNG" |
| |
| Location: |
Alexandria, Egypt |
| Start Date: |
1st of July, 2009 |
| Duration: |
One Year & Renewable |
Brief: |
Carry-Out the Preventive Maintenance, Corrective Maintenance, Predictive Maintenance and trouble shooting of HVAC Systems. |
| |
|
|
| Project: |
Advanced Chemical Cleaning for Metering Pipes |
|
| Client: |
Rashid Petroleum Company [Abo-Homos] |
| Location: |
Alexandria, Egypt |
| Start Date: |
July, 2009 |
| Duration: |
24 Hours excluding Mob and De-mob |
Brief: |
The Scope of work shall cover the chemical cleaning for the Metering Pipes using 'Advanced Industrial Chemical Cleaning Techniques', utilizing strongly effective and friendly advanced chemical products Kirasol 340 and Kirasol 318 SC. |
| |
|
|
| Project: |
Modify/Install of Davits Activities for life boat P-1 Platform |
|
| |
| Client: |
Rashid Petroleum Company |
| Location: |
Alexandria, Egypt |
Brief:
|
To dismantle the two old davits, modify the existing maintenance service platform and install the new davits for Rashid new safety boat located at Rosetta P-1 Platform as per the new construction drawing |
| |
|
| Project: |
Fire Fighting Activities |
|
| Client: |
Egyptian Operating Company for Natural Gas
Liquefaction "ELNG" |
| |
| Location: |
Alexandria, Egypt |
Brief:
|
The scope of work represents the supply & installation and commissioning of a complete system of automatic fire fighting by means of Sprinkler heads C/W interconnecting pipes and controls , sprinkler heads with all piping , fittings and controls. |
| |
| |
|
| Project: |
Module Replacement in Abo Madi & Port Fouad |
|
| Client: |
Belayim Petroleum Co. "Petrobel" |
| Location: |
Damietta, Egypt |
Brief:
|
The scope of work represents "Turbo Compressor- Gas Turbine Replacement" by a new one; This module replacement was the first to be done in Egypt and it was done in a safe and professional way which yielded clients' appreciation for the professionalism of EMC Personnel to execute the required activities. |
| |
|
|
|